On August 13, 1996, the Environmental Protection Agency (EPA) took Whitewood Creek off its Superfund list, finding that the site “poses no significant threat to public health or the environment.” About 30 million tons of gold-mill tailings had gone into the creek over more than a century. This page covers what the Black Hills’ older mines left behind: the tailings on Whitewood Creek, the acid water at the Gilt Edge Mine, the abandoned uranium mines of the southern Hills and the Cave Hills, what the cleanups have cost and who has paid, and the reclamation that the record shows worked.
What Happened on Whitewood Creek?
Whitewood Creek received the waste of Northern Hills gold mills for more than 100 years, until the practice ended in 1977. EPA’s 1995 notice names the Homestake Mining Company of Lead as the largest contributor and puts the tailings in the creek’s floodplain at an estimated 30 million tons. They carried arsenic and other metals: copper, zinc, selenium and mercury. The mine’s story is on The Homestake Mine and Sanford Lab; the town on the creek is Whitewood, South Dakota.
The site covers the floodplain of an 18-mile stretch of the creek, from the Crook City bridge to the Belle Fourche River, across Lawrence, Meade and Butte counties. EPA placed it on the National Priorities List, the Superfund list, on September 8, 1983. A Record of Decision in March 1990 chose a limited remedy: remove or cover tailings-contaminated soil where people live, and limit access to the tailings and groundwater. Homestake carried it out under a consent decree signed in August 1990. In 1991 and 1992 the company cleaned 16 residential yards and moved 4,500 cubic yards of contaminated soil to an on-site disposal area.
The tailings themselves stayed where they lay. Butte, Meade and Lawrence counties passed ordinances in 1992 and 1993 barring new homes or businesses on tailings deposits, and the state banned shallow water wells in the floodplain. Homestake must re-test the cleaned yards at least every five years and clean them again if arsenic exceeds 100 milligrams per kilogram of soil. EPA wrote in 1996 that contamination remains and that cleaned yards could be recontaminated, so five-year reviews are required. The state describes a 30-year maintenance phase that began with the deletion. The notices give no dollar figure for the cleanup. EPA’s third five-year review, signed in 2012, put upkeep at roughly $40,000 to $66,000 a year for 2007 to 2011. It found the remedy protective in the short term and asked for two fixes: more vegetation on the disposal area, and repair of three properties whose protective fabric layer had been breached and not fixed within the one year the maintenance plan allows. The sources read for this page do not include the reviews after 2012.
What Is Whitewood Creek Like Now?
EPA’s 2019 reuse profile says about 83 percent of the site is still native woodland and that the creek banks have been replanted. The land serves as ranchland, and the creek is used for irrigation, livestock and recreation. The creek is in use, and tailings remain in its floodplain under legal restrictions.
What Is the Gilt Edge Mine, and Why Is It a Superfund Site?
Gilt Edge is a 360-acre site in Lawrence County, where mining and ore processing began in 1876. The last operator, Brohm Mining Company, stopped in 1999. Surface mining exposed sulfur-bearing rock, which produces acidic drainage carrying zinc, cadmium, nickel and copper into surface water and groundwater.
The collapse was visible a year ahead. In May 1998 South Dakota won an emergency order to stop Brohm from abandoning treatment of ponds holding sulfuric acid and cyanide. The state said the company’s $6 million cash bond fell about $4 million short of what cleanup would need. The president of Brohm’s parent, Dakota Mining, answered that delays to a 1994 expansion proposal had put the company in financial jeopardy. The parent went bankrupt, and in 1999 the state moved the $6 million bond into a state account to pay for reclamation. A state official later said the bond was “severely under-calculated.” EPA and the federal Bureau of Reclamation took over water treatment from the state on August 1, 2000, and EPA listed Gilt Edge on the National Priorities List on December 1, 2000.
Who Has Paid for Gilt Edge?
The public has paid most of it. Federal and state governments had spent more than $100 million by August 2020, about $120 million by September 2023, and more than $120 million by September 2024, according to South Dakota Public Broadcasting (SDPB). Upkeep runs about $2 million a year. The federal government pays 90 percent of cleanup costs and the state 10 percent, SDPB reported in 2023.
Mining companies have paid part. On October 9, 2012, EPA, South Dakota and several companies settled in federal court for $30.2 million: Cyprus Mines Corporation, Cyprus Amax Minerals Company and Blue Tee Corp. together owed $26 million, and Homestake Mining Company of California $4.2 million. A separate consent decree entered in September 2016 brought in just over $10 million more from Coca Mines, Inc. and its former president, for EPA’s past costs. EPA’s case summary describes Brohm as insolvent in the late 1990s. The sources read for this page do not break the total spending down by payer. The Canadian company Agnico Eagle held a lease with EPA and the state that traded exploration rights for cleanup work. It reports contributing $5.25 million since 2018, and it announced in September 2024 that it would end the lease, saying the economics did not meet its threshold.
The work is not finished. The acid drainage will need treating far into the future: an EPA official told SDPB in 2023 that the treatment process will go on beyond the official’s own lifetime, and that acid mine drainage in general can last for hundreds of years. As of September 2024, the latest schedule found, EPA planned to update the design, bid the job and secure funding for further capping of the waste, with construction starting in 2028.
What About the Abandoned Uranium Mines?
The Forest Service’s Riley Pass site, in the North Cave Hills of Harding County, has the clearest record. Uranium exploration began there in 1954, strip mining ran from the mid-1950s to the early 1960s, and all mining in the area stopped by 1964. Twelve bluffs, about 300 acres in all, hold spoils with elevated arsenic, molybdenum, thorium, uranium and radium-226, and runoff carries sediment off site. The Forest Service calls the conditions “an imminent and substantial endangerment” to health and the environment.
Kerr-McGee, the predecessor of Tronox, was notified of possible liability in 1996. Tronox went bankrupt in 2009, and an initial settlement gave the Forest Service funds to start; a 2014 settlement between Anadarko, which had acquired Kerr-McGee, and the United States pays for cleanup at Kerr-McGee sites including Riley Pass. The Forest Service page gives no dollar amounts. As of March 27, 2026, it lists reclamation done on most of the bluffs between 2010 and 2020, with three still open: bluff B (153 acres, work begun in 2022), bluff H (34 acres) and bluff L (10 acres).
In the southern Hills, the Edgemont mill that processed the area’s ore is covered in Edgemont, South Dakota. For one abandoned mine about 13 miles north-northwest of town, the Darrow, Freezeout and Triangle mine in Fall River County, EPA’s record says the agency assessed it, found it did not qualify for the National Priorities List on existing information, and decided that no further federal action will be taken. That is a screening decision, not a cleanup, and the record gives no date. The sources read for this page give no full count of abandoned uranium mines in the southern Hills. What a new uranium mine would add is argued on Uranium Mining Around the Black Hills.
What Reclamation Has Worked?
Some of it has, and the record says so. At Gilt Edge, a 62.9-acre geosynthetic cap finished in 2003 on the Ruby Gulch waste rock repository cut acid drainage from that source by about 80 percent, according to the state’s Department of Agriculture and Natural Resources (DANR). Water treatment continues, but the cap did what it was built to do.
Whitewood Creek is a second case. Yards were cleaned, EPA found no significant threat in 1996, and ranches and woodland occupy the floodplain today, within the limits above.
A third is the large gold mines. DANR records the state releasing operators from reclamation liability on reclaimed ground: 499.74 acres at Homestake in 2006, 401 acres at Golden Reward in 2009, 265.94 acres at Richmond Hill in 2015, and 44.02 more acres at Homestake in 2018. Its running total for Black Hills large-scale gold mines was 1,201.05 acres in its 2015 entry, before the 2018 release.
At Edgemont, the Department of Energy reports that 137 properties were certified to federal standards and released for unrestricted use, and that about 4 million tons of mill waste sit under a 9-foot cover, with a grazing license on the site since 2006. Whether the cover holds is what annual inspections test; no inspection finding was read for this page.
What Do Bonds Cover?
A bond is money an operator sets aside before mining so the state can reclaim the land if the operator cannot. At Gilt Edge, $6 million was not enough. At Homestake, DANR records a post-closure surety of $47,797,929 in 2018. At the working Wharf mine, regulators raised the bond from $64 million to $95 million in 2020, with the state pointing to Gilt Edge as the reason, and the board gave Coeur Mining until December to post the added $31 million. Wharf and the newer exploration projects are covered in Gold, Lithium and the New Mining Rush; the town where Homestake worked is Lead, South Dakota.
Connected
- The Homestake Mine and Sanford LabThe largest source of the Whitewood Creek tailings, from claim to laboratory.
- Lead, South DakotaThe town above the creek and the mine.
- Whitewood, South DakotaThe town on the creek the tailings flowed down.
- Edgemont, South DakotaThe uranium mill and the disposal cell south of town.
- Gold, Lithium and the New Mining RushWharf and the exploration projects, and the bonds behind them.
- Uranium Mining Around the Black HillsThe mines, the aquifers and the Dewey-Burdock proposal.
Sources
- National Priorities List: Notice of Intent to Delete the Whitewood Creek Site. Environmental Protection Agency, Federal Register, 1995.
- National Priorities List: Deletion of the Whitewood Creek Site. Environmental Protection Agency, Federal Register, 1996.
- Superfund Sites in Reuse in South Dakota. Environmental Protection Agency, entries updated 2019.
- South Dakota Minerals, Mining, and Superfund. South Dakota Department of Agriculture and Natural Resources.
- Third Five-Year Review Report for Whitewood Creek. Environmental Protection Agency, Region 8, 2012.
- Case Summary: EPA Recovers Over $10 million for Cleanup Costs at the Gilt Edge Mine Superfund Site. Environmental Protection Agency, 2016.
- Case Summary: EPA Recovers Over $30 million for Past Costs at the Gilt Edge Superfund Site. Environmental Protection Agency.
- A look inside efforts to clean up mining industry black eye. South Dakota Public Broadcasting, 2023.
- Agnico Eagle terminates Superfund site mine lease. South Dakota Public Broadcasting, 2024.
- State raises gold mine’s bond by $31 million. Seth Tupper, South Dakota Public Broadcasting, 2020.
- Big mines leave a big mess. High Country News, 1998.
- Riley Pass Uranium Mine. U.S. Forest Service, Custer Gallatin National Forest, 2026.
- Darrow/Freezeout/Triangle Uranium Mine. Environmental Protection Agency, Superfund site profile.
- Edgemont, South Dakota, Disposal Site Fact Sheet. U.S. Department of Energy, Office of Legacy Management, 2026.
Last reviewed: